Lindian Sources Ltd (ASX:LIN, OTC:LINIF) has moved the Kangankunde Uncommon Earths Mission in Malawi deeper into execution mode, inserting orders for key long-lead processing tools whereas ramping up parallel building workfronts throughout earthworks, infrastructure and web site readiness.
The corporate has positioned procurement orders for important processing packages, together with the SAG mill, thickener and flocculation plant, shaking tables and belt filters, in a transfer designed to enhance schedule certainty as building exercise accelerates.
Lindian recognized the SAG mill because the principal long-lead merchandise on the mission’s important path, with an estimated supply timeframe of about 22 weeks. The thickener and flocculation plant package deal is anticipated inside roughly 14 weeks, whereas shaking tables and belt filters carry supply home windows of round 20 weeks, inclusive of manufacture, testing and transport.
“Seeing greater than 550 folks on web site working throughout a number of workfronts safely, and reaching 200,000 LTI-free hours, is a powerful reflection of the tradition and self-discipline we’re constructing at Kangankunde,” Lindian Sources govt director Zac Komur mentioned. “This mission is now firmly in execution mode, enabling earthworks are nicely superior, key infrastructure is progressing, and we now have positioned orders for the important long-lead plant packages to lock in supply timing and shield the schedule. The mission is aligning to the grasp schedule, with course of plant building and mine stripping commencing in February, first blast in April, grid energy energisation in July, and concentrating on first ore feed and first focus in November 2026. Our focus is simple: do the work safely, management the important path, and ship a high-quality uncommon earth mission with tempo and certainty.”
Aerial view of the positioning administration precinct beneath building, together with the admin constructing and web site medical clinic, supporting operational readiness as web site exercise ramps up.
On-site exercise continues to ramp up, with greater than 550 personnel now working throughout a number of workfronts as bulk earthworks, entry roads and trafficable platform preparation progress towards the primary building section.
Lindian is deploying its owner-operator Komatsu fleet to take care of momentum and restrict reliance on third-party contractors, with the identical tools supporting haul highway growth, platform formation and Tailings Storage Facility earthworks as a part of a lower-capital execution technique.
Komatsu HM400 articulated dump vehicles hauling fill as earthworks progress throughout the Kangankunde web site, supporting preparation of building platforms and entry routes.
Supporting workforce mobilisation, building of the 90-person Tipume lodging camp is advancing and anticipated to be out there in late February. Administration buildings, a web site medical clinic and safety amenities are additionally nearing completion.
As web site exercise will increase, Lindian reported reaching 200,000 lost-time-injury-free work hours, marking a key security milestone in the course of the mission’s transition into full execution.
The corporate reaffirmed its grasp schedule, with near-term and main milestones now guiding the important path. These embrace course of plant building and mine stripping in February 2026, first blast in April 2026, grid energy energisation in July 2026, and first ore feed and first focus focused for November 2026.
Waiting for March, Lindian expects a step-change into full building execution, together with completion of early civil web site institution, graduation of course of plant building, and mobilisation for structural, mechanical, plateworks and piping scopes.
Different March milestones embrace completion and supply of the workshop package deal, mobilisation of key building help tools, graduation of perimeter fencing, and completion of the explosives journal package deal forward of full drill-and-blast operations.
Upcoming March 2026 milestones
Processing plant and web site institution
Civil web site institution for early civils works completes to allow the primary building ramp-up.
Course of plant building begins a significant step-change from early works into execution.
Website institution begins for structural/mechanical/plateworks/piping scope.
Procurement and building help
Procurement / ordering / receiving supplies completes for the workshop package deal workstream
Building help tools telehandlers, HIAB truck, 55t crane scheduled to begin on web site helps building productiveness.
Website infrastructure and safety
Website extensive perimeter fence building commences
Explosive journal package deal reaches mission full milestone important path precursor to full drill- and-blast operations.
Camp and admin amenities ending works
A number of buildings transfer by way of finishes in March brick/blockwork wrapping early March, then ceilings, plaster, tiling, plumbing, portray by way of to end-March